Fifth residents’ newsletter – Beatrice Tate


From Victor Soulié (Site manager)

This is our fifth residents’ newsletter which will give you an update on the Beatrice Tate School project.

Structural works are progressing well and are planned to be complete for the New Year. The facade finishes such as the windows, render and brickworks have commenced while the internal trades are scheduled to start in November.

We would also like to inform you that Bouygues UK is taking part in the
UK Contractors Group (UKCG) Open Doors Weekend on Friday 9″‘ and Saturday 10″‘ November 2012. This event aims at providing an insight for the public into the construction industry. On both days, you will have the opportunity to visit our site and learn about the various elements of the Beatrice Tate School project in the presence of the architect and the production team. We believe that this event will also inspire young people to consider pursuing careers in construction.

If you are interested in visiting the site during the event you can apply via the Open Doors website: www.opendoorsweekend.co.uk

Our website will provide you with more information about our work at Beatrice Tate School and in the borough:   www.bouygues-projects.co.uk/beatrice-tate-school

For your information, all newsletters are available on the above website and displayed on the hoarding for your reference. (Download PDF – click here)